Which document outlines the specific deliverables for a project?

Disable ads (and more) with a premium pass for a one time $4.99 payment

Study for the UiPath Automation Business Analyst Professional Exam with detailed questions, hints, and explanations. Prepare confidently and excel in your certification!

The project scope document is crucial as it explicitly outlines the specific deliverables for a project. It serves as a foundational element that defines what will be included and excluded in the project. This document details the goals, features, tasks, deadlines, and resources needed, effectively providing a roadmap that guides the project team throughout its lifecycle. By setting clear expectations about what is to be delivered, it helps to prevent scope creep and ensures that all stakeholders have a shared understanding of the project objectives.

The other choices do not serve the same purpose. A project readiness checklist focuses on the preparations needed before initiating the project, ensuring that all conditions are met to start. A business case provides the justification for the project, discussing the rationale, benefits, and potential costs but does not detail specific deliverables. A change request, on the other hand, is a document that proposes alterations to the project scope or deliverables after the project has started, rather than outlining them from the outset. Thus, the project scope document is the definitive source for project deliverables.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy